You are currently viewing June 4, 2021 – K. Graney Podcast: Business Update

PODCAST

Hi everyone, it’s Kevin.  It’s Thursday, June 3rd (date recorded).

This morning, USS Hartford arrived at the shipyard for its Engineering Overhaul (EOH).   The contract to overhaul the Hartford was awarded to EB last August.  During negotiations, the contracting team and the Navy determined that a preparatory approach to this overhaul known as a ‘Smart Start’ would help EB make pre-availability preparations that would help us deliver the boat back to the fleet as soon as possible.

The EOH work is scheduled to start in February of next year.  Between now and then, the boat will be dry docked here in Groton, and pre-overhaul work, including inspections, testing and system teardowns will be performed to enable a strong, on-time start next year.  The Department of Defense will officially announce the award of the ‘Smart Start’ later this week—we expect tomorrow.

Overhaul and repair work is vitally important to EB.  It allows us to manage ebbs and flows in the workload here in Groton associated with the Virginia and Columbia programs, and enables our workforce to maintain proficiency in crucial skills—particularly RADCON, as it applies to boats of the fleet.  A Smart Start on the Hartford is the right approach to maintain and modernize the ship and get it back to the fleet.   I’d like to commend the team, led by Jim Belz, for ensuring this contract negotiation was successfully completed. Great job, guys.

The Hartford is now docked at the North Wing Wall.  If you look at the Groton Waterfront, you’ll note that for the first time in several years, both graving docks and wing walls are occupied.  The Hartford joins the South Dakota and Delaware, both here for their PSAs, and the Vermont, undergoing some emergent work prior to sea trails.  In a word, we are full at the south-end of the yard.

Our landscapes at both locations in Groton and Quonset have undergone significant changes, and the Facilities team has reached milestones worth noting in the past several weeks.

In Groton:

  • The concrete structural deck on the South Yard Assembly Building was completed last Thursday, May 27th.  We’ve received our first deliveries of steel beams, trusses and roof decks, and erection of the structure began on Wednesday.  From my office, up here on the 10th floor of Building 88, you can see the first pieces of structure peeking out over the south yard ways already.
  • In the middle of this month, we’ll break ground on Building 604 in Groton, which will house EB’s Radiological Emergency Response Team, locally-based Naval Reactors personnel, and the Emergency Command Center.  That building is scheduled to be complete in late 2022.

And in Quonset Point:

  • We completed the 78,000 square-foot Columbia frame and cylinder building, known as AFC II, ahead of schedule earlier this month. We’re in the process of installing the APCO fixtures in the building now.
  • The new heavy lift pad on the Quonset waterfront is complete – this is where we will turn units from vertical to horizontal at Quonset Point – and we are erecting the first of two cranes.  This pad and cranes will enable transport of Columbia modules to the new barge for transport to Groton.  Construction of the pier has also commenced and we expect this job to be done by the end of the year.
  • We are also on track to complete facility improvements to the Quonset Point pipe packaging facility by the end of July.

The busy waterfront and rapidly-expanding facilities are visible evidence of our historic backlog.  It remains critical for all of us to remain focused on our personal contributions to meeting our collective goals: safety first, without question—quality, schedule, cost and continuous improvement, in that order.

Thanks for listening, everyone.  We’ll talk again soon.

Groundbreaking Ceremony Marks Start of USS Groton Sail Monument

Fifty years after the USS Groton (SSN‑694) first launched, dozens gathered outside the Groton Public Library Oct. 9 to celebrate the groundbreaking of the USS Groton Sail Monument. The $6.6 million project—three decades in the making—will honor the men and women who design, build, operate and maintain the Navy’s submarines, as well as the families...Continue reading→

A Celebration of Heart, Community and Victory

2026 American Heart Association Eastern Connecticut Heart Walk Recap Saturday, October 3, 2026 | UConn Avery Point The 2026 American Heart Association Eastern Connecticut Heart Walk at UConn Avery Point was nothing short of extraordinary. Under bright autumn skies, 26 incredible Electric Boat teams and 151 walkers came together with passion, purpose, and unstoppable energy...Continue reading→

Electric Boat Joins Regional Leaders for Military Appreciation Breakfast

Electric Boat employees joined military and community leaders for the Chamber of Commerce of Eastern Connecticut’s annual Military Appreciation Breakfast on Sept. 30 at Ocean Beach Park’s Port ‘N’ Starboard. The event provided more than 120 complimentary seats to active-duty service members from the Navy, Coast Guard and Connecticut National Guard. General Dynamics Electric Boat...Continue reading→

803 Section 2B/5 Transported from Quonset Point to Groton

PCU Arizona’s (SSGN 803) Section 2B/5 was successfully delivered to Groton from Quonset Point. At 184 feet in length, this section – which includes the Virginia Payload Module (VPM) – is the largest Virginia-class shipment ever transported. Arizona, the first submarine to incorporate VPM, will be about 460 feet long upon final construction. Section 2B/5...Continue reading→