You are currently viewing March 16, 2022 – K. Graney Podcast–Facilities Update with Joe Drake

PODCAST

Hi everyone; it’s Kevin. Today is Wednesday, March 16th.

Last week we held the topping-off ceremony for the South Yard Assembly Building (SYAB), when the final roof truss was lifted and set into place. This 200,000 square-foot building will be home to about 1,400 of us shipbuilders working to deliver Columbia to the Navy. That work will begin in the building sometime next year, and it will be in full-bore production in about the 2027 timeframe.

Today joining me is Joe Drake (JD), our Vice President of Real Estate and Facilities, and he’s going to provide us an update on the South Yard project and the other buildings going up across Quonset Point and Groton as part of our almost $2 billion dollar facilities expansion project.

So Joe, congratulations to you and your team on meeting this milestone; I know we’ve been eager to see this, and we’re making some great progress on the building.  I know you’re looking forward to it opening during the first quarter of next year. Let’s talk about the work that’s going on between now and then to get the building ready for final assembly and test of Columbia.

JD: Thanks Kevin. It’s a great time to be here at Electric Boat. 2022 is going to be a significant year for us as we continue to transition and prepare ourselves for the start of assembly and test of Columbia here in Groton. We are in the final year of construction of the South Yard Assembly Building. As you have noted, we have achieved several significant milestones already. Recently, we set the last truss atop the structure and had our topping-out celebration. We also set our land-based steam boiler, and within two weeks we will have permanent power to our transfer station along Eastern Point Road. In addition, some upcoming construction milestones include:

  • We will be starting the installation of the north mega doors next week;
  • The Utility Building will be weather-tight by the end of March;
  • The SYAB itself will be weather-tight by mid-June;
  • We are rapidly moving forward with our installation of mechanical, electrical, plumbing and life-safety equipment in the building; it’s kind of hidden from view now as the panels are going up, but there is a significant amount of work going on inside the building in anticipation of that work being ready for us to start construction. We anticipate most of that work will be in place by the end of September, and we will be testing and commissioning our systems the last quarter of this year in anticipation of receiving a temporary certificate of occupancy by the end of December. That will allow us to start outfitting in the building and moving forward and getting ready for Columbia;
  • We will start installing the 100-ton and 170-ton cranes this summer also; that really is our critical path; we’ve got to have those cranes in place so we can move cylinders around inside the building;
  • We’re looking forward to a Final Certificate of Occupancy on the first of February of next year.

I walked the building with Devin Xenelis yesterday, and you can see the amount of work that’s actually going on internally with all the piping, cabling and ventilation ducting, so appreciate that update. The overall Columbia program is something we’ve been working on for 15 years now, so it’s exciting to think about how the SYAB is going to be open in less than a year. This week our new barge Holland made its first trip up to Quonset Point. I know it was there this morning, and we continue construction on our floating dry dock, which is named the Atlas, down at Bollinger Shipyards in Louisiana. Those are the same shipbuilders who built the barge for us.

In addition to the South Yard, you’re doing some work with your team on a couple of buildings that we broke ground on in Groton last year—the new Emergency Control Center and the COATS pre-commissioning unit crew building in the South Yard. Let’s talk about those buildings.

As I said, 2022 is an exciting year. We are rapidly approaching completion of the ECC building; we anticipate completion by the end of July. The building is weather-tight, we are installing windows, exterior insulation and in the next week or two the metal panels. We are nearly completed with framing the interior and have started hanging drywall. Mechanical, electrical, plumbing and life-safety systems are progressing very well. We’re looking forward to completing that project and moving people in in September.

We have also started construction for the COATS/PCU Building. Excavation of the perimeter footers is complete, and we have started excavation of the interior footers. We are placing concrete for those footers as we speak. Steel is due to arrive at the end of April with erection beginning the first of May. The project is projected to be complete by the end of March of 2023. When you think about it, three buildings in Groton starting in the end of July, end of December and then March—it’s going to be a different skyline here.

No question; the skyline is already changing and will continue to change. Great to hear the progress, and I can’t wait to have those buildings complete. We’re looking forward to having a significantly modern facility to support particularly our ability to respond to potential emergencies. So that ECC building is one I’m eager to get moved into.

Now, moving from Connecticut, let’s talk a little bit about what we’re doing up at Quonset Point. We’ve changed the skyline there in many ways. In 2020 we completed buildings 9A and 9B, which gave us an additional eight acres of production space for Columbia and the VPM modules. It’s getting pretty full; there’s still some room to expand into I think. Let’s update folks on the building construction status at QP, including the new advance manufacturing project, what we call our AMP building. That building will enable QP to supplement our missile tube manufacturing capability.

Yes, we continue to change the landscape at Quonset Point.

The AMP project is going very well. The erection of steel is about 50% complete. We anticipate starting to hang insulated metal panels in the next couple of weeks. We are on track for a December 2022 delivery of this building with first use anticipated in the second quarter of 2023.

We’ve also commenced design of the final phase of the 9-series building, which will add another five acres of production space for Columbia and VPM. We anticipate a late-fall construction start, we have demolished Building 16, so we’ve already changed the skyline. The building is scheduled for delivery early in the second quarter of 2024.

We have also started design on the third Coatings facility. The construction schedule is similar to 9C. We will start the building in early winter and complete that project also late second quarter 2024.

Thanks for the update Joe. And Happy Birthday, I know you celebrated your birthday earlier this week. Thanks for taking the time to share the progress on a lot of these construction projects that have been underway for quite some time.

I think it’s important for people to understand that General Dynamics has a lot of decisions that they can make with where to invest their capital money. I think everybody here should be proud of the fact that General Dynamics has chosen to invest nearly $2 billion dollars here at Electric Boat, because they believe in our future, they believe in the work we do and the importance of submarines to our national security. You should be proud to know that your corporation is investing a considerable amount of money in our future. I’m looking forward to celebrating all of these building openings over the next couple of years in Groton and Quonset Point. 

If you can’t tell from me, I will tell you, it’s an exciting time to be a shipbuilder—we’re about 17% complete already on Columbia and advance construction for the second ship, Wisconsin, began last May. So it’s already here. I’ve asked you all this question before, and I’ll ask it again now—where else would you rather be than right here, right now at Electric Boat?

Thanks everyone; we’ll talk again soon.

Kevin

Safety Update: Installation of Speed Tables on Eastern Point Road

In an effort to increase safety at Electric Boat’s Groton shipyard, two speed tables are being installed across Eastern Point Road this week. The tables, a few inches tall and marked with yellow stripes, are designed to slow vehicle traffic in an area frequented by pedestrians. The first speed table crosses Eastern Point Road just...Continue reading

EB firefighters recognized for life-saving rescues

Five members of the Electric Boat Fire Department in Groton were recognized for perilous, life-saving rescues during a pair of multi-alarm fires that engulfed apartments in Groton and New London in 2025. Firefighters Thomas Gugliotti, Arthur Keaten, Theodore Bartkoski, James Brady and Capt. Ryan Boulanger were each presented with Lifesaving Awards and the prestigious 2026...Continue reading

The Barnacle: Parking Enforcement That Sticks

Meet the Barnacle, Electric Boat’s newest parking-enforcement tool that will begin deployment in the Groton shipyard starting Monday, June 15. As our enterprise continues to grow, we are dedicated to ensuring parking is safe, fair and accessible to all. The Barnacle is an immobilizing parking-enforcement device that attaches directly to a vehicle’s windshield using heavy-duty,...Continue reading

Honoring the U.S. Army Birthday

June 14th marks the 251st Birthday of the United States Army, a moment to honor the enduring legacy, bravery, and sacrifice of those who have worn the Army uniform since 1775. As the oldest branch of the U.S. military, the Army has played a vital role in shaping our nation’s history and safeguarding its freedoms....Continue reading

Rayha Report Ep. 20: 2026 EB Signing Days

Electric Boat held recent Signing Day ceremonies at Cranston West High School on May 21 and the Garde Arts Center in New London on May 28. EB President Mark Rayha spoke with students about their decision to join EB and educators who prepare their students for careers in shipbuilding. Click here to see the latest installment of the Rayha...Continue reading

Save the Date: CT Health Fairs Kick Off June 9

A Message From Dan Vieira and Kathleen Heller At EB, Safety and Wellness go far beyond meeting basic compliance standards. Our focus is on building a culture where employees can thrive in every aspect of their lives. Prioritizing wellbeing is vital to being our best on the job and at home with our families. ​​...Continue reading

Supporting Our Neighbors Impacted by The Ledges Apartments Fire

Early Sunday morning, a devastating fire occurred at The Ledges Apartments in Groton. Eighteen fire departments, including Electric Boat’s, responded.  Thanks to the heroism of these first responders no residents were injured. The fire did, however, displace more than approximately 50 residents and destroyed or damaged 44 units in the building. Several EB employees were...Continue reading

Pride Month Celebrations at Electric Boat

June 1st marks the start of Pride Month, a time for millions of LGBTQ+ individuals and allies around the world to come together in celebration and reflection. From film festivals and art shows, to marches and concerts, Pride is a vibrant tribute to LGBTQ+ culture, history and the relentless spirit of activism. It’s a chance...Continue reading

Celebrating Our Next Generation of Shipbuilders

The Next Generation of Shipbuilders Takes the Stage Over the past two weeks, Electric Boat welcomed the next generation of shipbuilders at our Rhode Island and Connecticut Signing Day celebrations, marking the beginning of a journey that will help shape the future of our company and our nation’s defense. Held at Cranston High School West...Continue reading

Update: Gold Star Bridge Project – Upcoming Traffic Impacts

CT DOT is preparing to enter the next major phase of the Gold Star Memorial Bridge Rehabilitation Project, and employees should expect new traffic patterns that may affect travel to and from EB’s Groton and New London facilities. A crossover will direct two northbound lanes onto the southbound bridge, as shown in this CT DOT...Continue reading