You are currently viewing March 16, 2022 – K. Graney Podcast–Facilities Update with Joe Drake

PODCAST

Hi everyone; it’s Kevin. Today is Wednesday, March 16th.

Last week we held the topping-off ceremony for the South Yard Assembly Building (SYAB), when the final roof truss was lifted and set into place. This 200,000 square-foot building will be home to about 1,400 of us shipbuilders working to deliver Columbia to the Navy. That work will begin in the building sometime next year, and it will be in full-bore production in about the 2027 timeframe.

Today joining me is Joe Drake (JD), our Vice President of Real Estate and Facilities, and he’s going to provide us an update on the South Yard project and the other buildings going up across Quonset Point and Groton as part of our almost $2 billion dollar facilities expansion project.

So Joe, congratulations to you and your team on meeting this milestone; I know we’ve been eager to see this, and we’re making some great progress on the building.  I know you’re looking forward to it opening during the first quarter of next year. Let’s talk about the work that’s going on between now and then to get the building ready for final assembly and test of Columbia.

JD: Thanks Kevin. It’s a great time to be here at Electric Boat. 2022 is going to be a significant year for us as we continue to transition and prepare ourselves for the start of assembly and test of Columbia here in Groton. We are in the final year of construction of the South Yard Assembly Building. As you have noted, we have achieved several significant milestones already. Recently, we set the last truss atop the structure and had our topping-out celebration. We also set our land-based steam boiler, and within two weeks we will have permanent power to our transfer station along Eastern Point Road. In addition, some upcoming construction milestones include:

  • We will be starting the installation of the north mega doors next week;
  • The Utility Building will be weather-tight by the end of March;
  • The SYAB itself will be weather-tight by mid-June;
  • We are rapidly moving forward with our installation of mechanical, electrical, plumbing and life-safety equipment in the building; it’s kind of hidden from view now as the panels are going up, but there is a significant amount of work going on inside the building in anticipation of that work being ready for us to start construction. We anticipate most of that work will be in place by the end of September, and we will be testing and commissioning our systems the last quarter of this year in anticipation of receiving a temporary certificate of occupancy by the end of December. That will allow us to start outfitting in the building and moving forward and getting ready for Columbia;
  • We will start installing the 100-ton and 170-ton cranes this summer also; that really is our critical path; we’ve got to have those cranes in place so we can move cylinders around inside the building;
  • We’re looking forward to a Final Certificate of Occupancy on the first of February of next year.

I walked the building with Devin Xenelis yesterday, and you can see the amount of work that’s actually going on internally with all the piping, cabling and ventilation ducting, so appreciate that update. The overall Columbia program is something we’ve been working on for 15 years now, so it’s exciting to think about how the SYAB is going to be open in less than a year. This week our new barge Holland made its first trip up to Quonset Point. I know it was there this morning, and we continue construction on our floating dry dock, which is named the Atlas, down at Bollinger Shipyards in Louisiana. Those are the same shipbuilders who built the barge for us.

In addition to the South Yard, you’re doing some work with your team on a couple of buildings that we broke ground on in Groton last year—the new Emergency Control Center and the COATS pre-commissioning unit crew building in the South Yard. Let’s talk about those buildings.

As I said, 2022 is an exciting year. We are rapidly approaching completion of the ECC building; we anticipate completion by the end of July. The building is weather-tight, we are installing windows, exterior insulation and in the next week or two the metal panels. We are nearly completed with framing the interior and have started hanging drywall. Mechanical, electrical, plumbing and life-safety systems are progressing very well. We’re looking forward to completing that project and moving people in in September.

We have also started construction for the COATS/PCU Building. Excavation of the perimeter footers is complete, and we have started excavation of the interior footers. We are placing concrete for those footers as we speak. Steel is due to arrive at the end of April with erection beginning the first of May. The project is projected to be complete by the end of March of 2023. When you think about it, three buildings in Groton starting in the end of July, end of December and then March—it’s going to be a different skyline here.

No question; the skyline is already changing and will continue to change. Great to hear the progress, and I can’t wait to have those buildings complete. We’re looking forward to having a significantly modern facility to support particularly our ability to respond to potential emergencies. So that ECC building is one I’m eager to get moved into.

Now, moving from Connecticut, let’s talk a little bit about what we’re doing up at Quonset Point. We’ve changed the skyline there in many ways. In 2020 we completed buildings 9A and 9B, which gave us an additional eight acres of production space for Columbia and the VPM modules. It’s getting pretty full; there’s still some room to expand into I think. Let’s update folks on the building construction status at QP, including the new advance manufacturing project, what we call our AMP building. That building will enable QP to supplement our missile tube manufacturing capability.

Yes, we continue to change the landscape at Quonset Point.

The AMP project is going very well. The erection of steel is about 50% complete. We anticipate starting to hang insulated metal panels in the next couple of weeks. We are on track for a December 2022 delivery of this building with first use anticipated in the second quarter of 2023.

We’ve also commenced design of the final phase of the 9-series building, which will add another five acres of production space for Columbia and VPM. We anticipate a late-fall construction start, we have demolished Building 16, so we’ve already changed the skyline. The building is scheduled for delivery early in the second quarter of 2024.

We have also started design on the third Coatings facility. The construction schedule is similar to 9C. We will start the building in early winter and complete that project also late second quarter 2024.

Thanks for the update Joe. And Happy Birthday, I know you celebrated your birthday earlier this week. Thanks for taking the time to share the progress on a lot of these construction projects that have been underway for quite some time.

I think it’s important for people to understand that General Dynamics has a lot of decisions that they can make with where to invest their capital money. I think everybody here should be proud of the fact that General Dynamics has chosen to invest nearly $2 billion dollars here at Electric Boat, because they believe in our future, they believe in the work we do and the importance of submarines to our national security. You should be proud to know that your corporation is investing a considerable amount of money in our future. I’m looking forward to celebrating all of these building openings over the next couple of years in Groton and Quonset Point. 

If you can’t tell from me, I will tell you, it’s an exciting time to be a shipbuilder—we’re about 17% complete already on Columbia and advance construction for the second ship, Wisconsin, began last May. So it’s already here. I’ve asked you all this question before, and I’ll ask it again now—where else would you rather be than right here, right now at Electric Boat?

Thanks everyone; we’ll talk again soon.

Kevin

Remembering September 11

On September 11, 2001, the Twin Towers of downtown Manhattan’s World Trade Center and the Pentagon in Washington, D.C., were targeted in a series of coordinated attacks that would leave an everlasting imprint on our country’s psyche. As the events unfolded on that Tuesday morning, nearly 3,000 people lost their lives, over 600 were injured...Continue reading

Atlas Plaque Unveiled, Honoring Plank Owners at South Yard Ceremony

Employees who have worked on Atlas, EB’s new state-of-the-art floating dry dock, gathered in the South Yard on Wednesday, Aug. 26, to unveil a new bronze plaque recognizing the contributions of its plank owners. The event celebrated the teams who helped bring Atlas from Bollinger Shipyards in Louisiana to its arrival in Groton earlier this year. Atlas will play...Continue reading

Rayha Report Ep. 26: Waterford Campus Groundbreaking

EB President Mark Rayha reports from the groundbreaking of the new Waterford Campus, where innovation, engineering and workforce development will come together to support our mission. The new facility will help train hundreds of shipbuilders daily as EB continues to grow for future production demands.

Waterford Campus Groundbreaking Marks EB’s Next Step in Innovation and Workforce Growth

Electric Boat officially broke ground Friday on the Waterford Campus, launching the transformation of the former Crystal Mall into a center for innovation, engineering and high‑tech workforce development. EB President Mark Rayha underscored how the project will reshape the way the company designs, tests and builds submarines. Innovation is the key, he said. “There’s an opportunity to...Continue reading

Powering HeartStrong 50: Thank You, EB Teams—Let’s Keep the Momentum Going!

​Thank you to our incredible EB Heart Walk teams, our community partners, and everyone who joined the American Heart Association (AHA) Torch Journey photoshoot. Your enthusiasm and dedication made this milestone truly special. Now let’s keep our HeartStrong 50 energy going—our goal is 50 teams and $50,000 raised for the 2026 AHA Eastern Connecticut Heart Walk on October 3 at UConn Avery...Continue reading

Speed Cameras to be Installed in the City of Groton

The City of Groton Police Department announced that automated speed enforcement cameras will be installed at several locations throughout the city. The cameras will be installed after the required 30-day public notification period, which began on Aug. 7, 2026. Camera locations: Mitchell Street Thames Street Clarence B. Sharp Highway (Route 349) Police said the purpose...Continue reading

MDA Apprenticeship Application Now Open

Application Window: August 1, 2026 – August 31, 2026 The MDA Apprenticeship Program is a four-year initiative designed to develop a highly skilled workforce for Electric Boat. This program provides three years of on‑the‑job training alongside qualified subject matter experts, combined with classroom instruction across various technical disciplines. Participants gain advanced skills, broaden their expertise, and...Continue reading

Building 600 Tech Stop Relocation

On Monday, August 3, 2026, Facilities will be relocating the Tech Stop currently located in Building 600 4th Floor East to its new location in Building 130-01 Classroom 7. During this time, please utilize the alternate Tech Stop location: B708 (625 Long Hill Road) Hours: Monday – Friday: 7:00 am – 3:00 pm The tech stop will resume...Continue reading